About this calculator

Elastic stretch of a wireline cable under toolstring weight and overpull, and the tension at which the weak point is designed to part. Stretch is a depth-control problem and weak point is a safety one, but both come off the same tension, which is why they belong on one page.

  • Stretch from toolstring weight, cable weight and overpull
  • Weak point rating against measured surface tension
  • Safe working pull with the cable rating stated

Method

Needs review

Field units

ΔL = K × W × L ÷ 10⁶

Symbols

W
Tension at surface · lbf
L
Cable length · ft
K
Cable stretch coefficient · ft/1000ft/1000lbf
Bs
Cable breaking strength · lbf
ΔL
Cable stretch · ft
Pw
Weak point rating · lbf

Assumptions

  • K and the breaking strength are cable-specific manufacturer values. They are not reproduced here and must be taken from the cable's own datasheet, which is why this entry is marked for review.
  • Elastic stretch only. Permanent set from a previous overpull is not recoverable by calculation.
  • Tension is not constant along the cable — it is highest at surface, where the cable carries its own full weight, and falls with depth, so a single surface tension is an approximation over a long run.
  • A weak point is a designed failure. Its rating is a specification to be verified against the assembly actually made up, not a number to be computed.

Reference

Cable manufacturer technical data.

Worked example

Needs review

A toolstring on monoconductor at 11,200 ft, before setting on depth, with 2,400 lbf read at surface and K taken from the cable certificate.

Given

K
0.85 ft/1000ft/1000lbf
W
2,400 lbf
L
11,200 ft

Working

  1. 01Cable stretch
    0.85 × 2,400 × 11,200 ÷ 10⁶22.85 ft

Worth knowing

K is the cable manufacturer’s stretch coefficient and is a property of that drum of cable, not a constant — which is why this method is marked as needing review. The arithmetic above is checkable; 0.85 is an illustrative value, not a typical one for any cable size, so use the K on your cable’s certificate. Applying the surface tension over the whole length also overstates the stretch slightly, because tension falls with depth as the cable carries less of its own weight.

The arithmetic above is checkable. The relation it works is not yet: needs a completion engineer, or tables this repository does not hold. Treat the relation as an outline, not as a figure to work from.

Preview

A design preview of a calculator that is not built yet. Nothing here is behind a sign-in — there is nothing to sign in to.

Tell us you want this one

Interface

What it takes, and what it gives back.

Field units first, because that is what the programme and the daily report are written in. Where a quantity is dimensionless there is no metric column to fill.

Inputs

Inputs to the Wireline stretch calculator
SymbolQuantityFieldSI
WTension at surfacelbfN
LCable lengthftm
KCable stretch coefficientft/1000ft/1000lbf—
BsCable breaking strengthlbfN

Outputs

Outputs from the Wireline stretch calculator
SymbolQuantityFieldSI
ΔLCable stretchftm
PwWeak point ratinglbfN

Scope

When this is the wrong tool.

A right number from the wrong calculator is the failure worth designing against, so each of these names the condition rather than the calculator.

Logging

Related calculations.

The ones that tend to be done in the same sitting, and that share assumptions with this.

Planned

Logging

Depth correlation

CCL and gamma ray tied back to a reference log

Depth correction for a cased-hole run: matching casing collars and gamma-ray markers against the reference log, and carrying the correction through to a perforating or setting depth. The number that matters is the shift applied and the confidence in it, which is why both will be reported rather than a single corrected depth.

Sourced

Does this match how you actually work it?

The assumptions above are the part worth arguing with. If one of them does not hold on the wells you run, that changes what gets built and how.